This fifteen-week lateral support project undertaken for WBHO/Menlyn Maine included 450 00m3 of bulk earthworks; 8 000 metres of drilling soil nails to a depth of 14m; the installation of 2 690m2 of permanent lateral support walls; and 81 structural piles, ranging from 750mm to 10 150mm diameter. It was necessary to core through 270MPa rock to form the required sockets.

 